Live updates
New Community & Prayer Hall
A new prayer hall, madrasah classrooms, a women's section, library and community kitchen — built by the community, for the community.

Progress timeline
Phase 1 — Completed
Groundworks & foundations
Site cleared, piling finished and the reinforced concrete slab poured across the full footprint.
Phase 2 — Completed
Structural frame
Steel frame erected to roof level and the first floor decking installed ahead of schedule.
Phase 3 — In progress
Roof, dome & external envelope
Dome structure lifted into place. Stone cladding and glazing works are now underway.
Phase 4 — Upcoming
Interior fit-out
Wudhu facilities, underfloor heating, carpeting of the prayer hall and the library fit-out.